估算矩形或梯形沟槽的实方、松方体积和所需车次。
Swell is the percent you enter. Truck count rounds up from the loose volume. Local arithmetic only. This is a quantity or geometry estimate, not a code check and not a substitute for a licensed professional.
- Bank volume
- 15 m³
- Bank volume
- 19.619259 yd³
- Loose volume
- 18.75 m³
- Trucks
- 2
Bank volume is the geometric trench. Loose volume applies the swell percent you enter. Truck count rounds up from the loose volume.
使用方法: 挖方计算器
输入数据或选择文件,调整设置并生成结果。复制或下载之前,请检查结果。
限制与支持格式
输入内容在您的设备上处理。
英语技术说明
Swell is the percent you enter. Truck count rounds up from the loose volume. Local arithmetic only. This is a quantity or geometry estimate, not a code check and not a substitute for a licensed professional.
Estimate bank and loose excavation volume for a rectangular or trapezoidal trench, and the number of truck loads. Swell is the percent you enter. Truck count rounds up from the loose volume. Local arithmetic only. This is a quantity or geometry estimate, not a code check and not a substitute for a licensed professional.
A 10 m × 1 m × 1.5 m trench at 25% swell.